This is from a document presented at the "FCC Office of Engineering & Technology Meeting," dated May 25, 2023. - Moderator
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
PG&E Concerns well documented on the Record:
* Over 100 incumbents (including PG&E) have voiced concerns with
Unlicensed Use of 6 GHz
* Many concerns included technical analysis and papers showing basis for concerns
* 6 Real-World tests filed, all show impact to licensed microwave link’s
Fade Margin (FM)
* Latest is FirstEnergy/EPRI testing and analysis showing 4 dB
impact to FM from consumer deployed LPI APs at 2% penetration to
total APs
* Wi-Fi 7’s 320MHz channels will exacerbate the effect
* Impact to FM increases annual unplanned outage time (see graph based
on TIA-10)
* PG&E Operations would be significantly impacted at these levels of interference: Commissioned study of Impact vs Penetration
https://www.fcc.gov/ecfs/document/105270409018197/1